Skip to content
Friday, 27 November 2026 | DMRC Helpline: 155370
Gurgaon Metro Rail Gurugram Metro Guide & Jobs
Updates
Delhi Metro fares revised from 25 Aug 2025 — weekday fares now ₹11 to ₹64Gurugram Metro Phase 2 (Sector 9 – Cyber City) ₹1,662 crore civil package clearedChange between Yellow Line and Rapid Metro at SikanderpurHUDA City Centre is now Millennium City Centre GurugramDelhi Metro fares revised from 25 Aug 2025 — weekday fares now ₹11 to ₹64Gurugram Metro Phase 2 (Sector 9 – Cyber City) ₹1,662 crore civil package clearedChange between Yellow Line and Rapid Metro at SikanderpurHUDA City Centre is now Millennium City Centre Gurugram
Gurgaon Metro News

Old Gurugram Metro: ₹62 Crore Utility Tender Issued, Bakhtawar Chowk Double-Decker Stuck Over Design Dispute

October 30, 2026 · admin · 3 min read

Old Gurugram Metro ₹62 crore utility tender and Bakhtawar Chowk double-decker update graphic

Work on the Old Gurugram Metro is moving to the ground-preparation stage. Gurugram Metro Rail Limited (GMRL) has floated a ₹62 crore tender to shift underground utilities for Phase 2, but a design disagreement with the Gurugram Metropolitan Development Authority (GMDA) is holding up the planned double-decker flyover-metro at Bakhtawar Chowk.

₹62 crore tender for utility shifting

Before metro pillars can go up, pipelines and cables along the route have to be moved. The new tender covers:

  • Relocating water, sewer and gas pipelines
  • Shifting stormwater drains and electricity cables
  • Preparing traffic diversion plans and widening roads where needed
  • Coordinating with Gurugram Traffic Police during the works

The contractor will have nine months from the award to finish utility shifting. Doing this work separately and early is meant to keep it from delaying the main civil construction.

Main ₹1,662 crore construction tender: key dates

  • Corridor: about 15 km, Sector 9 to DLF Cyber City, 14 stations
  • Tender issued: 5 October 2026
  • Bids open: 9 November 2026
  • Construction period: 30 months from contract award

Bakhtawar Chowk double-decker: what’s the dispute?

At Bakhtawar Chowk, one of the busiest junctions in the city with over 10,000 passenger car units passing through, GMRL plans an integrated double-decker structure:

  • A six-lane elevated road (three lanes each way) about 8.5 m above the ground, roughly 800 m long
  • A metro viaduct and station on top, about 18 m high
  • Both levels supported on shared piers along the central median

GMDA wants space kept for a future six-lane underpass connecting Sector 47 with the road towards Medanta Medicity, and has withheld its no-objection certificate over the pier positions. GMRL says the revised design it submitted on 1 October already makes room for the underpass. Until the two agencies agree, final approval and the construction timeline for this junction remain on hold.

What commuters should expect

Once utility shifting begins, expect lane closures and diversions along Old Delhi Road, Bajghera Road, Palam Vihar and nearby sectors. We will post diversion details on our News page as soon as they are announced.

Related: Gurugram Metro Phase 2 gets ₹1,662 crore nod · Routes & Map

FAQs

What is the ₹62 crore Old Gurugram Metro tender for?

It covers shifting underground utilities along the Phase 2 route: water, sewer and gas pipelines, stormwater drains and electricity cables, plus traffic diversion plans and road widening where needed, so pillar work can start without delays.

How long will utility shifting take?

The contractor has nine months from the award of the contract to finish the work.

Why is the Bakhtawar Chowk double-decker on hold?

GMDA wants space kept for a future six-lane underpass linking Sector 47 with the road towards Medanta Medicity, and has withheld its no-objection certificate over the pier positions. GMRL says its revised design from 1 October already allows for the underpass. Until the two agencies agree, approval and the timeline for this junction are on hold.

Which roads will be affected during the work?

Once utility shifting begins, expect lane closures and diversions along Old Delhi Road, Bajghera Road, Palam Vihar and nearby sectors.

Related guides

Sources & Credits

This article is based on reporting from the following publications. All credit for the original reporting goes to them:

Official sources: Official project updates and tenders are published by Gurugram Metro Rail Limited (GMRL).

Information may change. Please verify timings and fares with the official operator before travelling.

1 comment

Leave a Reply

Your email address will not be published. Required fields are marked *